GT50 engine
Intensive work on the GT50 engine continues, with more and more elements undergoing or nearing the testing stage, some results actually surpassing our expectations.
During the GT50 engine development program we had an opportunity to take 9 kg out of the engine by removing the bevel gearbox at the front of the engine.
To do this we had to modify the way the engine sits in the fuselage. We’ve now modified the engine installation. The drivetrain has been largely updated and we’re now developing out an updated firewall solution to provide the fire containment we need around the engine for this updated configuration.
Compressor and combustor manufacture
We are currently manufacturing the GT50 test compressor, the one that will actually run in the gas generator and the power turbine tests that are going to take place later this year. This involves all the treatments, inspections, balancing of the wheels and then managing the clearances between the impeller tip and the stationary components. Over the next week or two we’ll be producing the first GT50 impeller to run in a test engine.
Blade and casing casting
To productionise the GT50 we now have to extend the already successful turbine blade casting process that resulted in good quality turbine blades that passed NDT inspections, to casings.
Blade root grinding
Through a multiple operation process, once we’ve ground the root and the wedges and the tips of the blades, then we’ve got a production grade aerospace turbine blade, all made in house by us through this palette of processes. We are about to start grinding the very first tree roots on Hill turbine blades.
Gas generator turbine disc testing
We’ve got the very first GT50 gas generator turbine disc in production right now, which will run in the test engine over the coming months. We’ve developed all of the CMM (coordinate measuring machine) and the non-destructive test processes (NDT) to be able to qualify that the disc has the necessary integrity and quality.
Annular combustor
We’ve also been working extensively on the production of the annular combustor, critical to make a compact, lightweight engine. The GT50 test combustor is in production, with all of the rolled parts now successfully manufactured. We’re just finishing the very last press tool for the components that can’t be rolled or spun and then we’re then left with the assembly and the welding, ready for the combustion test rig.
Starter generator
The GT50 prototype starter generator is also in production. The PMU or motor control unit has also been developed. All of the algorithms necessary to control the high frequency, high voltage AC electric that’s generated in 3 phases has been developed. We’ve also got the algorithms to drive the starter generator as a motor and we’ve been carrying out passive load testing on those algorithms using the electrical test bench.
The devices being built are expected to be ready about mid-April. We’re now in a position where the MGU, the starter generator hardware, is imminent. The control systems have been developed and the test rig is being shipped to us. By mid-April we should have both the GT50 starter generator and also the test bench to fully develop and qualify it.
FADEC
The GT50 FADEC system development board, the very first physical embodiment of our FADEC system, has now been built and delivered. The FADEC control laws have been developed and are now sitting on the FADEC board waiting to be tested with a model in the loop, and then later with hardware in the loop. It is just waiting for a gas generator to control, on the combustion test rig.
Combustion test rig and casing
The combustion test rig has been fired up for the first time, and the preliminary results we had were fantastic - a lot of the key parameters that we needed to see working in this first run worked beautifully. We can hold the flame stable; we can ignite reliably, and now we have to tune the fuel injection and the air blast atomiser to get that shape burning, get the chemistry of the combustion right and get that process working properly.
We’ve already learned a lot from this rig. In the next few weeks, we’ll have the fuel nozzles sorted, and the air blast atomisers, and that then freezes up ready to run in the full annular combustor and tested.
In preparation for the compressor, the turbine blades, and the turbine discs all coming together, we also need to ensure that the static components of the engine are ready for the gas generator test. We’re taking the same suite of processes we’ve developed for the blades and casting these sorts of enclosures to give us that low-cost production solution for really high integrity parts for the engine.
The very first GT50 combustion casing passed (with a healthy margin) a hydrostatic test to ensure that it can withhold all of the pressures it’s going to see in service.